Case Study 67: Metro Square Parking Lot

Case Study 67: Metro Square Parking Lot

Location:
Phoenix, AZ
Date:
May, 2014
Product:
4,025 Tons of FORTA-FI reinforced Hot Mix Asphalt
Contractor:
Ace Asphalt, Co Inc.


Application / Problem Description:
Complete asphalt pavement reconstruction

Solution:
The entire parking lot was replaced with FORTA-FI reinforced asphalt. The pavement section was reduced to 2 inches in the parking stalls and 3 inches in the drive lanes. This solution was chosen as it will lead to greater crack resistance and life extension. An inspection carried out two years after the installation indicated the presence of only two very small cracks across the entire lot. Following its impressive performance on this project, KIMCO has chosen to use this product exclusively on all their Arizona properties.